Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 297 discussion

Actual exam question from PMI's PMP
Question #: 297
Topic #: 1
[All PMP Questions]

During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment.
What type of analysis should the project lead have conducted to avoid this situation?

  • A. Benefits analysis
  • B. Risk analysis
  • C. Capacity analysis
  • D. Gap analysis
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
elrexyeoh
1 week, 4 days ago
Selected Answer: A
Benefits analysis
upvoted 1 times
...
Bruce_Liu
3 months, 3 weeks ago
Selected Answer: B
ChatGPT choose B and highlight is risk related.
upvoted 1 times
...
josephsafiran
3 months, 3 weeks ago
Selected Answer: B
The project lead should have conducted a B. Risk analysis. This type of analysis would have helped identify potential issues, such as high operational costs, that could pose a risk to the project. By identifying these risks early, the project team can develop strategies to mitigate them and avoid situations like the one described. However, it’s important to note that risk analysis should be an ongoing process throughout the project, as new risks can emerge at any time.
upvoted 1 times
...
vatsan1980
4 months, 2 weeks ago
since the question is abt Agile method Option A is correct
upvoted 1 times
...
examkitten
5 months, 2 weeks ago
Selected Answer: A
benefit analysis. it is all about the business value (compared with the cost).
upvoted 1 times
...
Lucky_Cindy
6 months, 1 week ago
Selected Answer: A
A , should do cost benefit analysis
upvoted 1 times
...
ChezQW
6 months, 1 week ago
Selected Answer: A
I believe the risk analysis would apply if the costs were affecting the project itself. This operational costs affects the product, not the project which is the exercise done to deliver a product based on the requested deliverables established based on the cost benefit analysis done which was an input to the Develop Project Charter process. If the cost benefit analysis done properly in the project benefits management plan, then the cancellation of features would not have been a possibility.
upvoted 3 times
...
Only12go
6 months, 2 weeks ago
Selected Answer: B
To avoid the situation where product features are at risk of being canceled due to high operational costs, the project lead should have conducted a: B. Risk analysis A risk analysis would help identify potential risks and issues associated with the operational costs of the product in a production environment. This analysis would involve assessing the likelihood and impact of such risks and then developing risk mitigation strategies to address them. It allows the project team to proactively manage and mitigate risks related to operational costs before they become critical issues that could lead to feature cancellations.
upvoted 1 times
...
jon0729
6 months, 2 weeks ago
Selected Answer: B
B: Risk Analysis would have given a chance to mitigate or avoid risk entirely.
upvoted 1 times
...
adingmaki
6 months, 2 weeks ago
I've searched the internet. No such thing as Capacity Analysis. (There is capacity planning which is not related by definition) Gap Analysis talks about performance. There is a Cost-Benefits analysis but no Benefits Analysis only. Risk Analysis https://www.pmi.org/learning/library/risk-analysis-project-management-7070 In the article, there is a cost related analysis.
upvoted 1 times
...
victory108
8 months, 3 weeks ago
Selected Answer: B
B. Risk analysis
upvoted 1 times
...
SteAle
10 months, 1 week ago
Selected Answer: A
Benefit analysis to compare the high operational costs to the potential benefits.
upvoted 2 times
...
aqz_111
11 months, 3 weeks ago
It is a question about reprioritisation so it is required to do benefit analysis. High business value should be included, so the answer is A
upvoted 2 times
...
JYKL88
1 year ago
Will go for C
upvoted 1 times
JYKL88
1 year ago
change of ans, should be A. need to conduct benefit analysis to avoid such situation
upvoted 1 times
...
...
Hung3102
1 year, 1 month ago
I think B
upvoted 1 times
...
RagazzoAlex
1 year, 2 months ago
why not B?
upvoted 1 times
...
BAKH
1 year, 3 months ago
pour la réponse ne figure pas dans les propositions. Il s'agit plutôt de l'analyse du coût de cycle de vie
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...