A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two.)
RevZig67
Highly Voted 2 years, 4 months ago21d5982
Most Recent 2 months, 3 weeks ago462729f
5 months, 1 week agoKim222
11 months, 2 weeks agod482858
1 year, 3 months agoKennyMuffins
1 year, 5 months agoloscoe
1 year, 8 months agoxcjxcj
1 year, 7 months agoOnly12go
1 year, 9 months agovictory108
1 year, 10 months agoAstridN
2 years, 1 month agoDawn6699
2 years, 1 month agoHung3102
2 years, 4 months agoPaulPMP
2 years, 4 months agoPMPStudent
2 years, 8 months agoPMPStudent
2 years, 8 months ago