A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.
What should the project manager do in this situation?
Hashi1_snr
Highly Voted 1 year, 6 months agoK91
Most Recent 3 months, 3 weeks agoAndrofred
4 months agovlxx
7 months agoYak_Yeti
4 months, 2 weeks agoprklg1
7 months, 2 weeks agoezzaariyouness
9 months, 1 week agonobuuu
1 year, 2 months agoOnly12go
1 year, 7 months agoLucky_Cindy
1 year, 7 months agoAsakthi
1 year, 9 months agopsvexam
1 year, 9 months agoKhoiCX
11 months, 3 weeks agoNA1234567
9 months, 3 weeks agoSteAle
1 year, 10 months agovictory108
1 year, 11 months agoAP2023S
1 year, 12 months agoPushkarRode
1 year, 10 months agoANAS3796
1 year, 12 months agosnagile
2 years agoGhibliTester
2 years ago