A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.
What should the project manager do in this situation?
Hashi1_snr
Highly Voted 1 year, 8 months agououa
Most Recent 4 days, 21 hours agoK91
5 months, 3 weeks agoAndrofred
6 months agovlxx
9 months agoYak_Yeti
6 months, 2 weeks agoprklg1
9 months, 2 weeks agoezzaariyouness
11 months, 1 week agonobuuu
1 year, 4 months agoOnly12go
1 year, 8 months agoLucky_Cindy
1 year, 9 months agoAsakthi
1 year, 11 months agopsvexam
1 year, 11 months agoKhoiCX
1 year, 1 month agoNA1234567
11 months, 2 weeks agoSteAle
2 years agovictory108
2 years, 1 month agoAP2023S
2 years, 1 month agoPushkarRode
2 years agoANAS3796
2 years, 1 month agosnagile
2 years, 2 months ago