exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 9 discussion

Actual exam question from PMI's CAPM
Question #: 9
Topic #: 1
[All CAPM Questions]

Select three processes that are associated with Project Schedule Management? (Choose three.)

  • A. Define Activities
  • B. Plan Resource Management
  • C. Estimate Activity Durations
  • D. Develop Schedule
  • E. Acquire Resources
Show Suggested Answer Hide Answer
Suggested Answer: ACD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
koryryan
11 months ago
Selected Answer: ACD
A,C, AND D
upvoted 1 times
...
jenza
1 year, 1 month ago
Selected Answer: ACD
A, C, and D
upvoted 2 times
...
bob523523
1 year, 2 months ago
Selected Answer: ACD
Option B (Plan Resource Management) and Option E (Acquire Resources) are not associated with Project Schedule Management. They are both associated with Project Resource Management.
upvoted 1 times
...
theplaceholder
1 year, 5 months ago
Selected Answer: ACD
Correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...