Actual exam question from PMI's CAPM
Question #: 15
Topic #: 1
[All CAPM Questions]

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

  • A. Initiating
  • B. Planning
  • C. Executing
  • D. Monitoring and Controlling
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Assad1981
7 months ago
B is best
upvoted 1 times
...
theplaceholder
1 year, 4 months ago
Selected Answer: B
After the project has been greenlit but before the work is actually done -- planning phase.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago