A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they feel it is a waste of time.
What should the project manager do?
e0cb955
3 months, 1 week agobetterthanyesterday
8 months, 1 week agoELTIGANI
1 year, 2 months agovictory108
2 years agoSteAle
2 years, 1 month agoAlizade
2 years, 4 months agoHung3102
2 years, 4 months agoDRohan
2 years, 4 months agoWeslineo
2 years, 6 months agoleo_gold
2 years, 8 months agoSASA2030
2 years, 8 months agoleo_gold
2 years, 7 months agosuflam3
2 years, 3 months agoTomGrey
2 years, 1 month ago8a6d137
2 months, 2 weeks ago