exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 659 discussion

Actual exam question from PMI's PMP
Question #: 659
Topic #: 1
[All PMP Questions]

A project manager is assigned to a multiyear project. During project execution, the customer delegates a new representative who contacts the project manager directly with a concern about their participation in status meetings. The representative wants to contact team members directly.

What should the project manager do next?

  • A. Send the new representative the approved project management and communications management plans.
  • B. Reach out to the customer directly for assistance in incorporating the new representative into the project management plan.
  • C. Meet with the new representative to determine their understanding of the project and address their concerns.
  • D. Meet with the project sponsor to discuss how to incorporate the new representative in the project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Only12go
7 months ago
Selected Answer: C
C. Meet with the new representative to determine their understanding of the project and address their concerns. By meeting with the new representative directly, the project manager can understand their perspective, clarify their role, set expectations, and ensure effective communication. This approach fosters collaboration and maintains the lines of communication open, ensuring alignment and understanding between all parties involved.
upvoted 1 times
...
victory108
7 months, 4 weeks ago
Selected Answer: C
C. Meet with the new representative to determine their understanding of the project and address their concerns
upvoted 2 times
...
zayn_1983
9 months ago
Selected Answer: D
D. new stakeholder, identify it in stakeholder register
upvoted 1 times
...
Thirukj
11 months, 3 weeks ago
Selected Answer: C
C is right
upvoted 1 times
...
ElshRote
1 year, 1 month ago
Selected Answer: C
While the customer's antics may be indicative of broader and deeper issues, it is important to meet with the new representative to determine their understanding of the project and address their concerns. In addition, the customer's antics portray insubordination and a smart PM must protect team members from such infiltrations which may pose distraction to the project.
upvoted 2 times
...
PMPStudent
1 year, 5 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...