exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 660 discussion

Actual exam question from PMI's PMP
Question #: 660
Topic #: 1
[All PMP Questions]

A team is preparing the closing phase and building a plan for the next phase. One of the project sponsors is complaining that the last phase had some quality deliverable issues. However, the quality acceptance document was signed.

What should the project manager do?

  • A. Postpone the next project phase until the impact of the quality issues is assessed.
  • B. Reopen the quality acceptance documentation to add the sponsor's complaints.
  • C. Schedule a quality review meeting and include the sponsor's complaints.
  • D. Review best practices and lessons learned and apply them to the project plan.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PMPStudent
Highly Voted 2 years ago
Selected Answer: C
C seems correct
upvoted 5 times
...
kkkyyyy
Most Recent 1 week, 2 days ago
Selected Answer: D
the correct answer is D
upvoted 1 times
...
Anssoo
1 month, 1 week ago
Selected Answer: D
D. Project is about to close and this additional complain should be captured in Lessons learned.
upvoted 1 times
...
Anssoo
1 month, 1 week ago
Selected Answer: D
D. Project is officially closed. New things should be added in next phase.
upvoted 1 times
...
ced45c8
11 months, 2 weeks ago
Selected Answer: D
PM is going to plan for the next phase, so he need to review best practice and include them in next phase planning.
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: C
C. Schedule a quality review meeting and include the sponsor's complaints
upvoted 2 times
...
ElshRote
1 year, 8 months ago
The acceptance document having been signed does not stop the project manager from scheduling a quality review meeting and documenting the sponsor's complaint. Not doing so will mean sweeping things under the carpet that may hurt the next phase.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...