Exam PMP topic 1 question 11 discussion

Actual exam question from PMI's PMP
Question #: 11
Topic #: 1
[All PMP Questions]

A project team consisting of four team members will be rolling out a company-wide application to both staff and contractors in a country. To deliver within strict the time lines, a local company skilled in application deployment and change management will need to be contracted.
What should the project manager do to empower the local company?

  • A. Manage expectations and agree on the requirements that the contractor will deliver under the supervision of the project manager
  • B. Begin to roll out the application by micromanaging the contractor
  • C. Set expectations and agree on the requirements that the contractor will deliver with periodic progress reports
  • D. Deploy the contractor's staff under the supervision of the project manager
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Aish_
Highly Voted 8 months, 4 weeks ago
Selected Answer: C
Option C emphasizes communication, collaboration, and regular updates through progress reports. It creates a structure for ongoing communication between the project manager and the local company, facilitating transparency and ensuring everyone stays informed about the project's status. While both Option A and Option C are reasonable approaches, they differ slightly in their emphasis. Option A emphasizes "supervision" by the project manager, which may involve a more hands-on approach. On the other hand, Option C highlights "periodic progress reports," which promotes regular updates and a collaborative working relationship between the project manager and the local company.
upvoted 9 times
...
Bhanu2086
Most Recent 2 days, 6 hours ago
Option C is the best approach as it sets expectation at the start and then periodically reviews the progress to evaluate the progress. This would also help the PM as he does not have to supervise constantly and he can utilize that time for other productive activities.
upvoted 1 times
...
Karan1102
2 weeks ago
The best option for the project manager to empower the local company is C. Set expectations and agree on the requirements that the contractor will deliver with periodic progress reports.
upvoted 1 times
...
BuviD
3 months, 3 weeks ago
Selected Answer: C
C. Set expectations and agree on the requirements that the contractor will deliver with periodic progress reports
upvoted 1 times
...
David983
6 months, 2 weeks ago
Selected Answer: A
I will go with A, The question saids "To deliver within strict the time lines" where I concluse that the supervision of the PM is much better to ensure the timeline is respected and the problems identified in advance than the periodic reports of the option C where delays will be discovered after happened
upvoted 4 times
ziyaetuk
6 months ago
...a local company skilled in application deployment and change management will need to be contracted. Skilled in averting the constrain...
upvoted 1 times
...
...
Tuanit
6 months, 3 weeks ago
Selected Answer: C
Since the question is how to empower local companies, with the constraint is that the project has strict timeline. C is the most appropriate answer. Set expectation and periodically verify the result would ensure both Empowering the local companies & Controlling progress
upvoted 2 times
...
AmeyAllam
7 months ago
Selected Answer: A
Its A because we want to empower the contractor , referring to self organized teams - therefore choosing the option that gives the team some kind of autonomy
upvoted 1 times
...
Alphy07
7 months, 3 weeks ago
A is correct
upvoted 1 times
...
mochips
8 months ago
Option A is correct. Inside the resource management plan, the local company has been identified as a resource provider. Expectations will be managed by the PM alongside requirements agreed with the local company.
upvoted 2 times
...
Mahi_02021988
8 months, 3 weeks ago
Answer is C
upvoted 1 times
...
Emmyomy
9 months ago
Selected Answer: C
Setting expectations is what the PM should do and also empower.
upvoted 1 times
...
Shivangi4444
9 months ago
c should be the answer.
upvoted 1 times
...
HoraceZzzz
9 months, 1 week ago
Selected Answer: A
Although project manager empower the local company, it does not mean Project manager will not manage or supervision.
upvoted 1 times
...
SteAle
10 months ago
Selected Answer: C
Answer C. The keyword here is "empower" - instead of micromanaging the PM should be checking on their performance on a periodic basis.
upvoted 2 times
...
hasanraza
10 months, 2 weeks ago
c is the answer
upvoted 1 times
...
victory108
11 months, 3 weeks ago
Selected Answer: C
C. Set expectations and agree on the requirements that the contractor will deliver with periodic progress reports
upvoted 2 times
...
JMCCRAY
11 months, 4 weeks ago
Selected Answer: C
C. Set expectations and agree on the requirements that the contractor will deliver with periodic progress reports. To empower the local company, the project manager should establish clear expectations and requirements for the contractor to deliver. This includes setting project timelines, milestones, and deliverables, as well as agreeing on how progress will be reported and monitored.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...