A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.
What should the project manager do?
achacyrille
Highly Voted 2 years, 5 months agoJamrock
1 year, 11 months agokavikris
8 months, 2 weeks agoDinesh1987
Highly Voted 2 years, 5 months agoTada00
Most Recent 2 months, 2 weeks agoPrincessviv96
4 months, 2 weeks agocrypto_dreams_medellin
9 months, 1 week agocrypto_dreams_medellin
9 months, 1 week agoArailym
11 months agosweety433
1 year, 2 months agoBhanu2086
1 year, 3 months agokraze29
1 year, 7 months agoBuviD
1 year, 7 months agoBuviD
1 year, 7 months agoThienDo93
1 year, 7 months agoGabMonterey
1 year, 8 months agoRajj98
1 year, 8 months agoPranav2204
1 year, 10 months agoNjabz_10
2 years agoJamrock
1 year, 11 months ago