A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.
What should the project manager do?
achacyrille
Highly Voted 2 years, 2 months agoJamrock
1 year, 8 months agokavikris
5 months, 1 week agoDinesh1987
Highly Voted 2 years, 2 months agoPrincessviv96
Most Recent 1 month, 1 week agocrypto_dreams_medellin
6 months agocrypto_dreams_medellin
6 months agoArailym
8 months agosweety433
11 months, 1 week agoBhanu2086
1 year agokraze29
1 year, 3 months agoBuviD
1 year, 4 months agoBuviD
1 year, 4 months agoThienDo93
1 year, 4 months agoGabMonterey
1 year, 5 months agoRajj98
1 year, 5 months agoPranav2204
1 year, 7 months agoNjabz_10
1 year, 9 months agoJamrock
1 year, 8 months agoSteAle
1 year, 10 months agoJamrock
1 year, 8 months ago