A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.
What should the project manager do?
achacyrille
Highly Voted 2 years, 3 months agoJamrock
1 year, 10 months agokavikris
6 months, 4 weeks agoDinesh1987
Highly Voted 2 years, 3 months agoTada00
Most Recent 4 weeks agoPrincessviv96
2 months, 3 weeks agocrypto_dreams_medellin
7 months, 2 weeks agocrypto_dreams_medellin
7 months, 2 weeks agoArailym
9 months, 2 weeks agosweety433
1 year agoBhanu2086
1 year, 2 months agokraze29
1 year, 5 months agoBuviD
1 year, 5 months agoBuviD
1 year, 5 months agoThienDo93
1 year, 5 months agoGabMonterey
1 year, 6 months agoRajj98
1 year, 7 months agoPranav2204
1 year, 9 months agoNjabz_10
1 year, 10 months agoJamrock
1 year, 10 months ago