A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.
What should the project manager do?
achacyrille
Highly Voted 1 year, 2 months agoJamrock
8 months, 1 week agoDinesh1987
Highly Voted 1 year, 2 months agoBhanu2086
Most Recent 1 week, 5 days agokraze29
3 months, 3 weeks agoBuviD
4 months agoBuviD
4 months agoThienDo93
4 months agoGabMonterey
5 months agoRajj98
5 months, 3 weeks agoPranav2204
7 months, 2 weeks agoNjabz_10
9 months agoJamrock
8 months, 1 week agoSteAle
10 months, 2 weeks agoJamrock
8 months, 1 week agorknowles
10 months, 2 weeks agoJamrock
8 months, 1 week agoAH1007
11 months, 1 week agovictory108
11 months, 4 weeks agoAnna12675
1 year agoshaharyarexamtopics
1 year, 1 month ago