A new major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings.
Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?
PMPStudent
Highly Voted 1 year, 4 months agonzili
Most Recent 1 week, 6 days agoBuviD
3 months, 4 weeks agoGabMonterey
5 months agoNelsned
7 months, 3 weeks agovictory108
11 months, 3 weeks agoAnna12675
12 months agoKRISHLM
1 year agoshaharyarexamtopics
1 year, 1 month agoCert_IT
1 year, 4 months agoGanzee
1 year, 4 months agoshaharyarexamtopics
1 year, 1 month ago