Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 43 discussion

Actual exam question from PMI's PMP
Question #: 43
Topic #: 1
[All PMP Questions]

A new major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings.
Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?

  • A. Assess the risk of the contractor not attending meetings and submitting reports for the rest of the project and escalate it to the project sponsor
  • B. Remind the contractor that they committed to attending meetings and submitting reports per the contract
  • C. Submit a claim for not fulfilling the contract terms and handle the claim in accordance with the alternative dispute resolution
  • D. Speak with the company's lawyer and request that they demand the contractor fulfill their contractual commitments
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
PMPStudent
Highly Voted 1 year, 4 months ago
Selected Answer: B
I am sticking with B
upvoted 6 times
...
nzili
Most Recent 1 week, 6 days ago
I'm going with B. The question is specific on contractual agreement, and the first thing after breaking the terms.
upvoted 1 times
...
BuviD
3 months, 4 weeks ago
Selected Answer: C
C. Submit a claim for not fulfilling the contract terms and handle the claim in accordance with the alternative dispute resolution
upvoted 1 times
...
GabMonterey
5 months ago
Selected Answer: B
answer is B. communicating first and try to remind and coach as well the subcon
upvoted 3 times
...
Nelsned
7 months, 3 weeks ago
All answers sound correct but the key phrase in this question is what to do first.
upvoted 1 times
...
victory108
11 months, 3 weeks ago
Selected Answer: B
B. Remind the contractor that they committed to attending meetings and submitting reports per the contract
upvoted 1 times
...
Anna12675
12 months ago
Selected Answer: D
d vote
upvoted 1 times
...
KRISHLM
1 year ago
option B
upvoted 1 times
...
shaharyarexamtopics
1 year, 1 month ago
B. Key word is what should PM do first. First thing is to remind the contractor.
upvoted 2 times
...
Cert_IT
1 year, 4 months ago
Selected Answer: B
I go with Option B
upvoted 4 times
...
Ganzee
1 year, 4 months ago
C. Submit a claim for not fulfilling the contract terms and handle the claim in accordance with the alternative dispute resolution
upvoted 2 times
shaharyarexamtopics
1 year, 1 month ago
Submit claim comes later stage not 1st thing to do.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...