A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.
What should the project manager do next?
cococua
1 month, 1 week agoPrincessviv96
4 months, 2 weeks agoMervy20
5 months agonqbaotd
8 months, 2 weeks agomohit05
11 months, 1 week agobabasoo
1 year, 5 months agoMuntadher
1 year, 6 months agovictory108
1 year, 8 months agoANAS3796
1 year, 8 months agoSarish07
1 year, 10 months agoterryp
1 year, 12 months agoCert_IT
2 years, 1 month agoGanzee
2 years, 2 months agoDedutch
1 year, 10 months ago