A project manager holds periodic progress review meetings to discuss issues.

What should the project manager do first on the agenda?

  • A. Elaborate the risk mitigation strategy and risk register.
  • B. Update resolution approaches and action assignments.
  • C. Formulate project management plan integration.
  • D. Produce lessons learned documentation.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Abdelmonm
9 months ago
Selected Answer: B
In periodic progress review meetings, it's essential to address current issues and challenges faced by the project. Updating resolution approaches and action assignments ensures that the project team is actively managing and resolving issues. This involves reviewing the status of previously identified issues, discussing the effectiveness of resolution approaches, and assigning or updating actions to address ongoing challenges. This proactive approach helps keep the project on track and allows the team to learn from experiences and continuously improve.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: B
B. Update resolution approaches and action assignments
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.