A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk. The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action_
Which document should the project manager review with their team?
leo_gold
Highly Voted 2 years, 7 months agojeepTango123456
2 years, 5 months agoPaulPMP
2 years, 3 months agoDzvuke
1 year, 7 months agoxcjxcj
1 year, 6 months agoKim222
Most Recent 11 months, 2 weeks agoPmpjune152024
1 year, 1 month agoompk
1 year, 2 months agoNadirJT
1 year, 3 months agoEfaChux
1 year, 4 months agoTrytrio
1 year, 5 months agoAbdelmonm
1 year, 5 months agoodylec
1 year, 7 months agoOnly12go
1 year, 9 months agoDavid983
1 year, 9 months agoSumbo
1 year, 9 months agoadingmaki
1 year, 9 months agovictory108
1 year, 9 months agoAish_
1 year, 11 months agoSteAle
1 year, 11 months agoDavid983
1 year, 9 months agoJune_buggy
2 years ago