Exam PMP topic 1 question 766 discussion

Actual exam question from PMI's PMP
Question #: 766
Topic #: 1
[All PMP Questions]

A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.

What should the project manager do?

  • A. Set up a stakeholder session with all teams to agree and document the benefits and establish ownership.
  • B. Ask the project sponsor to make a decision on who will own the benefit and document the decision.
  • C. Ask the project sponsor for approval to distribute the project benefits equally to the business areas.
  • D. Request all of the business areas to plan for a portion of the benefit equally and include it in their staffing plans.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
chlaithem
9 months, 3 weeks ago
Selected Answer: A
Transparency and fairness: Involving all stakeholders ensures a transparent and fair discussion about the potential benefits and their allocation. Shared understanding: A stakeholder session clarifies how the software's benefit (freed-up staff) can be utilized across different areas, preventing confusion and potential conflicts. Collaborative ownership: Documenting agreed-upon benefits and assigning ownership creates accountability and avoids ambiguity about how the resources will be used.
upvoted 1 times
...
odylec
10 months, 1 week ago
Selected Answer: A
A is the answer
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: A
A. Set up a stakeholder session with all teams to agree and document the benefits and establish ownership. In this situation, it's important to involve all relevant stakeholders in a collaborative manner to determine how the benefits of the new software will be distributed among the various business areas. Setting up a stakeholder session, as described in option A, allows for open discussion, agreement on the benefits, and the establishment of clear ownership. This approach ensures that the benefits are distributed in a fair and well-documented manner, taking into account the interests and needs of each business area.
upvoted 1 times
...
adingmaki
1 year ago
Selected Answer: B
A project sponsor is typically responsible for initiating, ensuring, approving, and establishing a series of key aspects in relation to the project, which can be summed up under categories of vision, governance, and value/benefits realization. FROM PMI. It's B
upvoted 2 times
...
adingmaki
1 year ago
All teams? Meat with all the teams? I'm really confused
upvoted 1 times
...
victory108
1 year ago
Selected Answer: A
A. Set up a stakeholder session with all teams to agree and document the benefits and establish ownership
upvoted 1 times
...
kevzzz
1 year, 5 months ago
Selected Answer: A
document the benefits and establish ownership
upvoted 3 times
...
Antony100
1 year, 6 months ago
A is the most appropriate option. This is because the new software implementation project will benefit several business areas, and it is important to ensure that all stakeholders are aware of the benefits and agree on how they will be realized and shared. By setting up a stakeholder session with all teams, the project manager can facilitate a discussion and agreement on the benefits, establish ownership for each benefit, and document the decisions made. This approach would help to ensure that all stakeholders are aligned and committed to realizing the benefits of the new software implementation.
upvoted 2 times
...
ElshRote
1 year, 7 months ago
The PO is part of the stakeholders. The PM is doing right to facilitate a meeting of all stakeholders involved since more business areas are going to benefit from the development. Such meeting will help with a resolution as to ownership as there will be contributions from diverse stakeholders rather than just the PO. Notice also that the discovery of who benefits was not just made by the PO but several business areas. Hence the importance of all stakeholders in the decision of benefit ownership.
upvoted 1 times
...
Leylandchan
1 year, 9 months ago
Selected Answer: B
Should it be "B"? Only sponsor has the right to decide who will be the end user of the project, not the PM or the end users themselves. Moreover, only sponsor can do the staffing, right?
upvoted 2 times
UppersquareCapital
9 months, 3 weeks ago
This approach (Option B) might lead to a decision that is perceived as unilateral and may not consider the perspectives and needs of all relevant business areas. However, with Option A, it's crucial to have a collaborative approach in determining how the benefits will be distributed and who will own them. This ensures transparency, consensus, and a clear understanding among the stakeholders about how the benefits will be allocated
upvoted 1 times
...
mrbottomwood
1 year, 7 months ago
(A) seems correct to me. Project sponsors are part of the "stakeholder" definition.
upvoted 3 times
...
...
15rajanikanthhotie
1 year, 10 months ago
Can someone explain?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago