Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?
Develop Schedule: We are analyzing the activities and plan a schedule model for executing and monitor... then we are planning not controlling. A control is when we compare the data agains the plan
Why the other options are incorrect:
B. Control Schedule: Focuses on monitoring the schedule and managing changes to the baseline — it’s about tracking, not analyzing to build the schedule.
C. Estimate Activity Durations: Involves estimating how long each activity will take — it doesn't analyze sequences or constraints.
D. Define Activities: Involves identifying and documenting the specific actions to be performed — it’s about listing tasks, not sequencing or analyzing them.
3.10 DEVELOP SCHEDULE
Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule
constraints to create a schedule model for project execution and monitoring and controlling. The key benefit of this
process is that it generates a schedule model with planned dates for completing project activities. This process is
performed throughout the project. The inputs and outputs of this process are depicted in Figure 3-11.
Page 575 - PMBOK 6
It is B because only Control Process includes Analyzing activity sequences.
Develop Schedule: This process is used to create the project schedule. It does not involve analyzing activity sequences, durations, resource requirements, and schedule constraints.
Estimate Activity Durations: This process is used to estimate the amount of time it will take to complete each activity. It does not involve analyzing activity sequences, durations, resource requirements, and schedule constraints.
Define Activities: This process is used to identify and define the activities that need to be performed to complete the project. It does not involve analyzing activity sequences, durations, resource requirements, and schedule constraints.
I correct myself: the process that analyzes activity sequences, durations, resource requirements, and schedule constraints is the Develop Schedule process.
Right answer is A: 6.5 Develop Schedule—The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
anfacer
Highly Voted 1Â year, 7Â months agoJesseChou_123
Most Recent 1Â month, 3Â weeks agoASCAPM
8Â months, 2Â weeks agoASCAPM
11Â months, 1Â week agoASCAPM
11Â months, 1Â week agotheplaceholder
11Â months, 3Â weeks agouyentran04
1Â year agoRocket20
1Â year agoDaiva
1Â year, 1Â month agobramirezb593
1Â year, 1Â month ago