exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 174 discussion

Actual exam question from PMI's CAPM
Question #: 174
Topic #: 1
[All CAPM Questions]

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

  • A. Develop Schedule
  • B. Control Schedule
  • C. Estimate Activity Durations
  • D. Define Activities
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
anfacer
Highly Voted 1 year, 7 months ago
Selected Answer: A
Develop Schedule: We are analyzing the activities and plan a schedule model for executing and monitor... then we are planning not controlling. A control is when we compare the data agains the plan
upvoted 6 times
...
JesseChou_123
Most Recent 1 month, 3 weeks ago
Selected Answer: A
Why the other options are incorrect: B. Control Schedule: Focuses on monitoring the schedule and managing changes to the baseline — it’s about tracking, not analyzing to build the schedule. C. Estimate Activity Durations: Involves estimating how long each activity will take — it doesn't analyze sequences or constraints. D. Define Activities: Involves identifying and documenting the specific actions to be performed — it’s about listing tasks, not sequencing or analyzing them.
upvoted 1 times
...
ASCAPM
8 months, 2 weeks ago
Selected Answer: A
3.10 DEVELOP SCHEDULE Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring and controlling. The key benefit of this process is that it generates a schedule model with planned dates for completing project activities. This process is performed throughout the project. The inputs and outputs of this process are depicted in Figure 3-11. Page 575 - PMBOK 6
upvoted 1 times
...
ASCAPM
11 months, 1 week ago
Selected Answer: B
It is B because only Control Process includes Analyzing activity sequences. Develop Schedule: This process is used to create the project schedule. It does not involve analyzing activity sequences, durations, resource requirements, and schedule constraints. Estimate Activity Durations: This process is used to estimate the amount of time it will take to complete each activity. It does not involve analyzing activity sequences, durations, resource requirements, and schedule constraints. Define Activities: This process is used to identify and define the activities that need to be performed to complete the project. It does not involve analyzing activity sequences, durations, resource requirements, and schedule constraints.
upvoted 2 times
ASCAPM
11 months, 1 week ago
I correct myself: the process that analyzes activity sequences, durations, resource requirements, and schedule constraints is the Develop Schedule process.
upvoted 1 times
...
...
theplaceholder
11 months, 3 weeks ago
Selected Answer: A
keep up
upvoted 1 times
...
uyentran04
1 year ago
there are many wrong answers on this platform! This should be A, not B
upvoted 3 times
...
Rocket20
1 year ago
Selected Answer: A
The Answer is A. 3.10 Develop Schedule
upvoted 1 times
...
Daiva
1 year, 1 month ago
why it says on this platform that the correct answer is B when surely it is A???
upvoted 1 times
...
bramirezb593
1 year, 1 month ago
Right answer is A: 6.5 Develop Schedule—The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...