A new project manager learns the work assigned to the team has already been decomposed to its lowest level. The project manager reviews the work and feels some additional, useful information is missing.
What should the project manager review?

  • A. The WBS dictionary
  • B. The requirements traceability matrix
  • C. The project charter and scope statement
  • D. The business requirement documents (BRD)
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Cert_IT
Highly Voted 1 year, 4 months ago
Selected Answer: A
A WBS dictionary is where the details of the tasks, activities, and deliverables of the work breakdown structure are located. The content includes whatever milestones are related, the project scope and in some instances dates, resources, cost and quantity
upvoted 7 times
...
Lucky_Cindy
Most Recent 6 months, 3 weeks ago
Selected Answer: A
WBS dictionary
upvoted 1 times
...
victory108
9 months ago
Selected Answer: A
A. The WBS dictionary
upvoted 1 times
...
modsjunk
1 year, 5 months ago
Selected Answer: A
Keyword here is decomposed to its lowest level which is a work item
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...