A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins to identify, evaluate, and categorize the stakeholder relationships to the program.
What is the purpose of this process?

  • A. Identify all stakeholders who can positively affect the project
  • B. Identify all stakeholders who can negatively affect the project.
  • C. Incorporate the needs of all stakeholders into the communications management plan
  • D. Incorporate only primary stakeholders into the communications management plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Muntadher
9 months, 2 weeks ago
Selected Answer: C
Need to add all stakeholder in communication management plan
upvoted 1 times
...
victory108
11 months, 2 weeks ago
Selected Answer: C
C. Incorporate the needs of all stakeholders into the communications management plan
upvoted 1 times
...
PMPStudent69
1 year, 3 months ago
Selected Answer: C
C correct
upvoted 2 times
...
Ganzee
1 year, 4 months ago
C. Incorporate the needs of all stakeholders into the communications management plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago