A vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.
What should the project manager do next?
modsjunk
Highly Voted 2 years, 6 months agoleo_gold
2 years, 5 months agoSuldan
Most Recent 1 month, 3 weeks agoAnne99
2 months, 1 week agoBegeego
7 months, 3 weeks ago6114c29
7 months, 3 weeks agoea4e1f8
9 months, 2 weeks agoKim222
9 months, 2 weeks agojosephsafiran
1 year, 5 months agoced45c8
1 year, 5 months agoPsadon
1 year, 6 months agoodylec
1 year, 6 months agoOnly12go
1 year, 7 months agoadingmaki
1 year, 8 months agovictory108
1 year, 9 months agoabdelilahfa
2 years agoJamrock
1 year, 10 months agoclarksu
2 years, 1 month agoadviselee
2 years, 1 month agoJamrock
1 year, 10 months agoadingmaki
1 year, 8 months agorajeshtk
2 years, 2 months agoaqz_111
1 year, 11 months ago