Exam PMP topic 1 question 407 discussion

Actual exam question from PMI's PMP
Question #: 407
Topic #: 1
[All PMP Questions]

A project manager receives a voicemail from a business analyst on the project team. The business analyst indicates that an internal stakeholder is upset that they were not included before the project began. The stakeholder is asking for an addition to the requirements traceability matrix.
What should the project manager do to improve the stakeholder relationship?

  • A. Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list.
  • B. Consult the project scope document to make sure the addition is in scope.
  • C. Engage the stakeholder to solicit more information before responding to the request.
  • D. Initiate a project change request so the change control board (CCB) can decide if it is in scope.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
amali999
10 months, 2 weeks ago
Selected Answer: C
A is wrong...they already the stakeholder
upvoted 2 times
segatarasov
8 months, 1 week ago
but it is clearly written that "an internal stakeholder is upset that they were not included before the project began"
upvoted 1 times
...
...
Lucky_Cindy
1 year ago
Selected Answer: C
C. Engage the stakeholder to solicit more information before responding to the request.
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: C
To improve the stakeholder relationship, especially when there is an indication that the stakeholder feels left out, it is essential to engage and communicate with the stakeholder directly. C. Engage the stakeholder to solicit more information before responding to the request. By directly engaging with the stakeholder, the project manager can better understand the stakeholder's concerns, needs, and expectations. This will provide an opportunity for the stakeholder to feel heard and valued, fostering a better relationship and improving collaboration. Once the project manager has a clear understanding of the request, they can then decide on the appropriate next steps, whether it be to update documents, initiate changes, or take other actions.
upvoted 3 times
...
David983
1 year ago
Selected Answer: C
I will go with C. Address the stakeholder interest very quickly will induce on stakeholder mindset change
upvoted 2 times
...
victory108
1 year, 2 months ago
Selected Answer: C
C. Engage the stakeholder to solicit more information before responding to the request
upvoted 3 times
...
kevzzz
1 year, 3 months ago
Selected Answer: C
Figure out the situation first by speaking with the stakeholder.
upvoted 2 times
...
GinniSingh
1 year, 3 months ago
Selected Answer: C
"stakeholder is upset that they were not included before the project began" - means now they are already part of stkhdr list... so no A.. only C
upvoted 3 times
...
leggoteam
1 year, 4 months ago
Selected Answer: C
Update before action, discuss before update
upvoted 2 times
...
SteAle
1 year, 4 months ago
Selected Answer: C
The PM should gather information first. From the question, it looks like the stakeholder is already identified.
upvoted 2 times
...
symea
1 year, 5 months ago
Selected Answer: C
First understand the stakeholder's concern and then check the stakeholder engagement plan to see if the stakeholder is properly entered.
upvoted 2 times
...
emelba
1 year, 7 months ago
The answer is C, you must decide by yourself if is necessary this stakeholder or not, not just obey orders, you are the PM
upvoted 3 times
...
sanjiiv
1 year, 7 months ago
Selected Answer: C
Can't be A since this stakeholder is already part of project stakeholder now.
upvoted 3 times
...
[Removed]
1 year, 7 months ago
C - Gather facts from the concerned stakeholder and narrow down their needs.
upvoted 2 times
...
Weslineo
1 year, 8 months ago
I think we need to engage the stakeholder first to know why he was omitted from the stakeholder list to find if truly he /she is met to be in the list,after that we update the stakeholder list.But first we must ENGAGE....
upvoted 4 times
...
AndyTokyo608
1 year, 8 months ago
Selected Answer: A
I think answer is A
upvoted 3 times
...
MBoo93
1 year, 9 months ago
Selected Answer: A
A, lest we shall forget this stakeholder again
upvoted 2 times
...
James10
1 year, 9 months ago
My guess is A. Can anyone explain why it's not?
upvoted 1 times
Jamrock
1 year, 3 months ago
adding a stakeholder to a document does not improve a relationship. that is the key ask in the question. Maybe if question asked what should you do first as the question may have made A. correct.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago