Exam PMI-PBA topic 1 question 5 discussion

Actual exam question from PMI's PMI-PBA
Question #: 5
Topic #: 1
[All PMI-PBA Questions]

After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?

  • A. Context diagram
  • B. Use cases
  • C. Tracing requirements
  • D. Process flow
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Proctored_Expert
1 year, 1 month ago
Selected Answer: C
C. Tracing requirements would have helped determine this issue before delivery. Tracing requirements is the process of linking project objectives to the specific requirements that are needed to achieve those objectives. By tracing requirements, the business analyst can ensure that all of the project objectives have associated requirements, and that those requirements are clearly defined and understood. This can help identify any gaps or missing requirements that may have been overlooked during the planning process.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...