During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
A.
interviewed to understand how the user’s work would be impacted.
B.
involved in the development and sign-off of the business requirements.
C.
given the opportunity to review the user acceptance test scripts.
D.
identified as a stakeholder as part of the stakeholder analysis.
D. identified as a stakeholder as part of the stakeholder analysis would have helped avoid this situation and minimize the impact on the project. Stakeholder analysis is the process of identifying the stakeholders in a project and analyzing their needs, interests, and influence on the project. By identifying all of the stakeholders in the project, the project team can ensure that their needs and concerns are taken into account during the planning and execution of the project. This can help minimize the risk of defects being logged during user acceptance testing, as all of the stakeholders will have had an opportunity to review and provide feedback on the project requirements.
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.PMI-PBA Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Proctored_Expert
11 months ago