Question #: 12
Topic #: 1
[All PMI-PBA Questions]

A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?

  • A. Sequence diagram
  • B. Requirements traceability matrix
  • C. Requirements attributes table
  • D. Project schedule and cost baseline
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Proctored_Expert
Highly Voted 1 year, 1 month ago
Selected Answer: B
The best option to determine the scope of the change on the product would be the requirements traceability matrix (option B). A requirements traceability matrix is a tool used to trace the relationships between the different requirements of a product, such as functional requirements, design requirements, and test cases. It helps to ensure that all requirements are properly traced and linked to the relevant design, implementation, and testing activities. This can be useful in determining the scope of a change to an existing feature, as it can help to identify which requirements are impacted by the change and what work needs to be done to implement it.
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...