A company’s management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices. The business analyst should:
A.
adhere to the project plan to achieve project objectives.
B.
clearly communicate project objectives and attempt to defuse tensions.
C.
delay the application’s deployment until the conflicts have been resolved.
D.
voice user concerns to management and recommend that the project be closed.
The best option to determine the scope of the change on the product would be the requirements traceability matrix (option B).
A requirements traceability matrix is a tool used to trace the relationships between the different requirements of a product, such as functional requirements, design requirements, and test cases. It helps to ensure that all requirements are properly traced and linked to the relevant design, implementation, and testing activities. This can be useful in determining the scope of a change to an existing feature, as it can help to identify which requirements are impacted by the change and what work needs to be done to implement it.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMI-PBA Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Proctored_Expert
1 year, 1 month ago