exam questions

Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

Exam PMI-PBA topic 1 question 24 discussion

Actual exam question from PMI's PMI-PBA
Question #: 24
Topic #: 1
[All PMI-PBA Questions]

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

  • A. Evaluate the solution against the project charter.
  • B. Conduct performance testing.
  • C. Evaluate the solution with the sponsor(s)
  • D. Conduct user acceptance testing.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Proctored_Expert
1 year, 1 month ago
Selected Answer: D
After the quality assurance team has passed the completed solution, the business analyst should conduct user acceptance testing. User acceptance testing (UAT) is a type of testing that is conducted to ensure that a solution meets the requirements and expectations of the end users. It involves having the end users test the solution and provide feedback on its functionality, usability, and overall performance. In this case, the business analyst should coordinate user acceptance testing to ensure that the solution meets the needs of the end users and is ready for deployment. This may involve working with the end users to develop test cases, coordinating the testing process, and gathering and analyzing feedback from the end users.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...