The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?
To evaluate a proposed requirement change after the product is baselined, the business analyst will need to conduct an impact analysis.
An impact analysis is a tool used to assess the potential impact of a change on a project or product. It involves identifying the potential impacts of the change on the project schedule, budget, resources, and deliverables, and evaluating the potential risks and benefits of the change.
In this case, the business analyst should conduct an impact analysis to evaluate the proposed requirement change and determine whether it should be implemented. This may involve reviewing the change request, identifying the potential impacts on the project or product, and assessing the risks and benefits of the change.
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PMI-PBA Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Proctored_Expert
10 months, 3 weeks ago