Question #: 674
Topic #: 1
[All PMP Questions]

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?

  • A. Resource leveling
  • B. Work breakdown structure (WBS)
  • C. Decomposition
  • D. Network diagram
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kmsinthesky
5 months, 2 weeks ago
Selected Answer: C
doing - i am doing decomposition of work (OK) Doing- i am doing WBS, (WBS is result not a process)
upvoted 3 times
...
certificate988
11 months ago
Selected Answer: C
work packages is part WBS. Here process is called decomposition.
upvoted 3 times
...
Jaya12
11 months, 4 weeks ago
Selected Answer: B
Creating a Work Breakdown Structure (WBS) involves breaking down the project work into smaller, more manageable pieces, typically represented as work packages. This helps in organizing and understanding the project scope, which is a fundamental step in project planning and management. Decomposition (option C) is a broader term and can involve breaking down work into smaller components. In this context, creating a WBS is a specific type of decomposition.
upvoted 2 times
...
Only12go
1 year ago
Selected Answer: C
The project manager is subdividing the project work packages, which means they are breaking down the project scope and deliverables into smaller, more manageable components. This process is known as "decomposition." When used in the context of creating a Work Breakdown Structure (WBS), decomposition refers to the act of breaking down the project scope into the hierarchical structure of the WBS, where each level represents an increasing level of detail. Therefore, the correct answer is C. Decomposition.
upvoted 2 times
...
ChezQW
1 year ago
Selected Answer: B
He is using the decompaction technique to create the WBS so the answer has to be B because they are asking what he is doing.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: C
C. Decomposition
upvoted 1 times
...
miggykurkova
1 year, 1 month ago
Decomposition project management is a process of breaking a large, complex project into smaller, more manageable parts. This technique can be used to decompose a project into smaller tasks or to decompose a large product into smaller component parts
upvoted 1 times
...
zayn_1983
1 year, 2 months ago
Selected Answer: C
C. the situation is in the process of create WBS, the tools to devide and subdividing the Project scope into smaller part is decomposition
upvoted 1 times
...
ilmi
1 year, 3 months ago
my answer is D, subdive the Work package means break down each of the work packages in into individual activities, After that the team created the activity list in the process of define activity, the next process should be sequencing the activities and the output is Project schedule network Diagram
upvoted 1 times
...
kevzzz
1 year, 5 months ago
Selected Answer: C
Decomposition as defined in PMBOK (5th Edition) is a tool and technique used to divide and subdivide the project scope and deliverable into more smaller, manageable work packages. Once the scope is decomposed, it’ll be the lowest level of WBS which can be estimated and managed in terms of cost and schedule. The size of the work package after decomposition will depend on the complexity and size of the project. At the time of decomposing, activities such as assigning identification codes to each work package will take place.
upvoted 2 times
...
RevZig67
1 year, 6 months ago
Selected Answer: B
The project manager is working on developing a Work Breakdown Structure (WBS), which is a hierarchical decomposition of the project work into smaller and more manageable work packages. So, the correct answer is B.
upvoted 2 times
...
mrbottomwood
1 year, 7 months ago
WBS: A WBS is a hierarchical breakdown of project deliverables and work packages. It is used to organize and define the scope of a project. It is created by breaking down the project deliverables into smaller and more manageable components. The WBS provides a framework for the project schedule and budget. It is typically presented in a chart format.
upvoted 1 times
mrbottomwood
1 year, 7 months ago
Decomposition: Decomposition is a technique used to break down a project into smaller, more manageable parts. It is used to define the activities required to complete a project. Decomposition is a part of the process of creating a WBS. It involves breaking down project deliverables into smaller components until they can be accurately estimated and managed. Decomposition can be used to create a hierarchical WBS or a linear task list.
upvoted 1 times
mrbottomwood
1 year, 7 months ago
This question is like asking which one of an identical twin is prettier! Anyhow I'd go with option B.
upvoted 1 times
mrbottomwood
1 year, 7 months ago
Keyword: "working with the project team to subdivide the project work packages." On a second thought, "subdivide the work packages", means a further breakdown of the work package NOT that the work is being divided among the team to know who's doing what! sheesh! I guess Decomposition is the answer!
upvoted 2 times
...
...
...
...
modsjunk
1 year, 10 months ago
Selected Answer: C
keyword here is subdivide also The lowest Levels of each Leg and Branch of the WBS are called Work Packages.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago