The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

  • A. Review the assumptions analysis
  • B. Create a risk response plan for those risks
  • C. Review the risk register to check for the new risks
  • D. Conduct a checklist analysis on each risk
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: C
Risk register outdated. We need to review the Risk Register again. We can “assume” that there are not new assumptions or assumptions needed for validation. Assumption analysis is something that you do at the beginning of the project or when the assumptions change constantly. This does not address the concern about the outdated risk register.
upvoted 1 times
...
IBANGA007
1 year, 11 months ago
Selected Answer: A
A. Review the assumptions analysis When the project sponsor asks the project manager about the accuracy of the project data, the project manager should review the assumptions analysis to ensure that the project data is accurate and up-to-date. The assumptions analysis is a tool that helps to identify and document the assumptions that are being made about the project, including assumptions related to risks. If the project manager realizes that some risks have not been updated recently, it is important to review the assumptions analysis to ensure that the project data is accurate and up-to-date. This may involve revisiting the risk register to check for new risks, conducting a checklist analysis on each risk, or creating a risk response plan for those risks. By reviewing the assumptions analysis, the project manager can help to ensure that the project data is accurate and that risks are being managed effectively.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...