Exam PMI-RMP topic 1 question 241 discussion

Actual exam question from PMI's PMI-RMP
Question #: 241
Topic #: 1
[All PMI-RMP Questions]

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

  • A. Risk identification
  • B. Risk analysis
  • C. Risk treatment
  • D. Risk evaluation
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SABAJANANADA
10 months, 4 weeks ago
B Risk analysis
upvoted 2 times
...
IBANGA007
11 months, 1 week ago
Selected Answer: B
B. Risk analysis If multiple workstreams are showing issues three months into a program, and the program manager requires that a risk impact assessment be conducted, it is likely that risk analysis will be the most effective approach for calculating the impact of these risks. Risk analysis is a process that helps to understand the likelihood and impact of identified risks, and to determine the appropriate risk response strategies. It involves evaluating the potential consequences of a risk, as well as the likelihood of that risk occurring. This helps to prioritize risks and focus risk management efforts on the most important risks.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...