Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
B. Risk analysis
If multiple workstreams are showing issues three months into a program, and the program manager requires that a risk impact assessment be conducted, it is likely that risk analysis will be the most effective approach for calculating the impact of these risks.
Risk analysis is a process that helps to understand the likelihood and impact of identified risks, and to determine the appropriate risk response strategies. It involves evaluating the potential consequences of a risk, as well as the likelihood of that risk occurring. This helps to prioritize risks and focus risk management efforts on the most important risks.
upvoted 3 times
...
This section is not available anymore. Please use the main Exam Page.PMI-RMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SABAJANANADA
10 months, 4 weeks agoIBANGA007
11 months, 1 week ago