A project manager was informed that the testing of the latest component in the project’s software update release was not successful. As a result, the delivery timelines for the software release will be delayed. The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

  • A. Add contingencies to other tasks to mitigate similar risks.
  • B. Review the risk response plan looking for lessons learned.
  • C. Reassess risks with a new assumptions and constraints analysis.
  • D. Log the event in the issue log and update the project management plan.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: D
You have an issue, you update the issue log and review the PMP (lessons learned, RMP, assumtions...) Then, you reassess risks with a new perspective.
upvoted 1 times
...
IBANGA007
1 year, 11 months ago
Selected Answer: C
The best answer would be C, reassess risks with a new assumptions and constraints analysis. When a risk event occurs that was not previously identified, it is important for the project manager to review the project's risk management plan and identify any potential gaps or weaknesses in the risk identification process. One way to do this is to perform a new assumptions and constraints analysis to identify any potential risks that may have been overlooked or underestimated. This can involve reviewing the project's assumptions, constraints, and dependencies, as well as examining any changes that may have occurred since the initial risk assessment was conducted. By performing a new assumptions and constraints analysis, the project manager can identify any new or emerging risks that may impact the project, and can develop appropriate response strategies to mitigate or reduce the impact of those risks. This can help to ensure that the project is able to effectively manage risks throughout the project lifecycle and avoid similar risks in the future.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...