An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50,000. Risk B has a probability of 0.7 and an impact of US$60,000. After implementing the planned risk response for risk B, the probability of risk B has been reduced to 0.3.
What is the current project risk exposure?
IBANGA007
11 months, 1 week ago