An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together. How should the facilitator proceed?
A.
Set up a lessons learned session from a similar project.
B.
Hold a team charter discussion.
C.
Schedule a release planning session.
D.
Conduct a product roadmap session with the team.
When working with a new team on a project, the Agile Facilitator should start by holding a team charter discussion. This session helps the team establish a shared understanding of the project's purpose, goals, and expectations. During the session, the team will discuss the scope of the project, the stakeholders involved, and the team's roles and responsibilities. This discussion will help the team align on the project's objectives, establish a foundation of trust, and identify potential risks and challenges.
MY thought process will be to hold a charter session first then follow up with a lesson learned session, as it will offer a roadmap on the project and clear understanding of project scope and timeline and key stakeholders so everyone is in alignment since this manager hasn't worked with the team before
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Hung3102
Highly Voted 1 year, 1 month agodeeps2023
9 months agoPrincessviv96
Most Recent 1 month agoductrinh
1 month, 2 weeks agoMuntadher
9 months, 2 weeks agovictory108
11 months, 2 weeks agoMobarak7
1 year ago