A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on
20 December might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.
What should the project manager do about this risk?
Jamrock
Highly Voted 1 year, 10 months agoAndrofred
Most Recent 4 months agoAmirov
6 months, 3 weeks agodiegovcz
9 months, 1 week agomohit05
1 year, 1 month agoTuanit
1 year, 7 months agoompk
1 year, 10 months agoWhiteTable
1 year, 8 months agoarseyam
1 year, 6 months agovictory108
1 year, 11 months agomazamaza
2 years agoMobarak7
2 years agodeeps2023
1 year, 9 months agoHung3102
2 years, 1 month agonovantuno
2 years, 4 months ago