A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress (WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.
What should the project manager have done to avoid this situation?
dickytricky
Highly Voted 2 years, 6 months agoParamak
Most Recent 1 year agoELTIGANI
1 year, 1 month agojosephsafiran
1 year, 6 months agoBruce_Liu
1 year, 6 months agoAbouemK
1 year, 7 months agoOnly12go
1 year, 9 months agoadingmaki
1 year, 9 months agoDavid983
1 year, 9 months ago4f6ae44
1 year, 3 months agoGoku_PMP
1 year, 11 months agovictory108
1 year, 11 months agosmartrammy
2 years agoSteAle
2 years agoSteAle
2 years agoOrochi
2 years, 1 month agoAP2023S
2 years, 2 months agosassy2023
2 years agoGoodluckZoe
2 years, 2 months agoaqz_111
2 years, 2 months ago