A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress (WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.
What should the project manager have done to avoid this situation?
dickytricky
Highly Voted 1 year, 4 months agojosephsafiran
Most Recent 3 months, 3 weeks agoBruce_Liu
4 months agoAbouemK
4 months, 3 weeks agoOnly12go
6 months, 2 weeks agoadingmaki
6 months, 2 weeks agoDavid983
6 months, 3 weeks ago4f6ae44
2 weeks, 1 day agoGoku_PMP
8 months, 2 weeks agovictory108
9 months agosmartrammy
10 months agoSteAle
10 months, 1 week agoSteAle
10 months, 1 week agoOrochi
11 months, 1 week agoAP2023S
11 months, 2 weeks agosassy2023
10 months, 1 week agoGoodluckZoe
11 months, 2 weeks agoaqz_111
12 months agoJMCCRAY
1 year agoHung3102
1 year, 1 month ago