Why the other options are incorrect:
B. Total costs incurred while accomplishing work – This describes Actual Cost (AC).
C. Budget associated with planned work – This refers to Planned Value (PV).
D. Cost efficiency of budgeted resources – This describes Cost Performance Index (CPI)
Key here 'work that has been completed' --> earned..