Why the other options are incorrect:
A. Brainstorming helps identify risks or ideas, not directly used for estimating durations. Monte Carlo simulation is more relevant for quantitative risk analysis. Analogous estimation is valid but not paired well with the other two here.
B. Resource leveling is a schedule development technique, not a duration estimation tool. Iteration burndown charts are Agile tracking tools, not duration estimation methods.
C. Milestone charts and schedule baselines are outputs, not estimation techniques.
Key word is estimation --> 'Parametric estimation, three-point estimation...'
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
JesseChou_123
1 month, 4 weeks agotheplaceholder
11 months, 4 weeks agoexamworld
1 year agopahkhu
1 year agoMFrankieG2022
1 year, 7 months ago