Actual exam question from PMI's PMI-RMP
Question #: 270
Topic #: 1
[All PMI-RMP Questions]

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

  • A. To enable the team in identifying the specific causes of risks associated with project objectives.
  • B. To ensure that project priorities are being appropriately factored into risk response plans.
  • C. To assign risks and risk severities to functional discipline and departments effectively.
  • D. To determine where more attentive project leadership and organizational involvement is needed.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 2 weeks ago
Selected Answer: B
B correct answer
upvoted 1 times
...
SABAJANANADA
1 year, 11 months ago
B is the correct answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...