A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the appropriate stakeholder participation and involvement level required for successful project delivery.
What should the project manager do?

  • A. Communicate with the stakeholders to find a solution.
  • B. Review the issue log with the project stakeholders.
  • C. Evaluate the stakeholder engagement assessment matrix.
  • D. Perform a stakeholder assumption and constraint analysis.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: C
C. Evaluate the stakeholder engagement assessment matrix
upvoted 1 times
...
victory108
9 months, 3 weeks ago
Selected Answer: C
C. Evaluate the stakeholder engagement assessment matrix
upvoted 1 times
...
Alizade
1 year, 1 month ago
Selected Answer: C
The stakeholder engagement assessment matrix is a tool that can help the project manager evaluate the level of stakeholder participation and involvement required for a successful project. This matrix is a useful tool for understanding the stakeholders' level of interest, power, and influence, and can help the project manager determine the most appropriate level of engagement for each stakeholder. By using this tool, the project manager can develop a stakeholder engagement plan that outlines how each stakeholder will be involved in the project and to what extent. This can help ensure that all stakeholders are adequately engaged, which can help improve project outcomes.
upvoted 3 times
...
Adeshola1960
1 year, 4 months ago
Selected Answer: C
C. Evaluate the stakeholder engagement assessment matrix. With a large number of stakeholders involved in a project, it's important for the project manager to have a clear understanding of their engagement and involvement levels. To address this concern, the project manager should evaluate the stakeholder engagement assessment matrix. This matrix should include information such as the stakeholders' roles and responsibilities, level of involvement, and communication needs. This will help the project manager to understand the level of participation required from each stakeholder for successful project delivery.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...