A project team is conducting sprint planning. At the end of the sprint, the product increment must be deployed on a customer's site. The product owner received an email from the account manager that the customer may not be ready to install the new version of the product.
What should the project manager do?
21d5982
1 month, 1 week agojosephsafiran
11 months, 3 weeks agoLucky_Cindy
1 year, 2 months agoOnly12go
1 year, 2 months agoadingmaki
1 year, 2 months agoFyrus
1 year, 2 months agoStella104
1 year, 4 months agovictory108
1 year, 4 months agoAde134
1 year, 5 months agoDavonos
1 year, 4 months agoSteAle
1 year, 5 months agosassy2023
1 year, 5 months agoemelba
1 year, 9 months agoktwin1973
1 year, 7 months agoSolid_Jehuty
1 year, 8 months agoSolid_Jehuty
1 year, 8 months agoJYKL88
1 year, 8 months agoAdeshola1960
1 year, 11 months ago