A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team. What should the project manager do?
A.
Ask the team member to bring up the concern in the next daily meeting
B.
Send an email explaining the issue to all team members
IMHO: A is the best answer considering the senario
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Princessviv96
4 months, 2 weeks agoGabMonterey
8 months, 2 weeks agoTracyyy123
10 months, 1 week agoSketchie
11 months agoMuntadher
1 year agovictory108
1 year, 2 months agoMobarak7
1 year, 4 months agoPMPStudent69
1 year, 7 months ago