exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 96 discussion

Actual exam question from PMI's PgMP
Question #: 96
Topic #: 1
[All PgMP Questions]

You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

  • A. Program administrative closure
  • B. Enterprise environmental factors
  • C. Closing processes
  • D. Organizational process assets
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
c9619c8
3 weeks, 3 days ago
Selected Answer: C
Closing processes are the formal procedures and activities required to finalize all aspects of a program, including completing forms and paperwork as mandated by the organization before the program can be officially closed.
upvoted 1 times
...
UHS
2 years ago
Answer needs to be C - EEF has nothing to do with the closing
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel