A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.
Which scheduling method should the project manager use to develop the schedule?
ElshRote
Highly Voted 1 year, 9 months agocwilson91
1 year, 6 months agoAbdelmonm
Most Recent 11 months, 3 weeks agoOnly12go
1 year, 3 months agoadingmaki
1 year, 3 months agovictory108
1 year, 3 months agoAcmk
1 year, 4 months agoKelvin12312
1 year, 4 months agomiggykurkova
1 year, 4 months agoAYZ
1 year, 4 months agoAish_
1 year, 5 months agoSteAle
1 year, 5 months agomdadewale
1 year, 5 months agokevzzz
1 year, 8 months agospamgayy
1 year, 9 months agoRevZig67
1 year, 9 months agoSathy
1 year, 10 months agoRagaa
1 year, 12 months ago