A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.
Which scheduling method should the project manager use to develop the schedule?
ElshRote
Highly Voted 1 year, 7 months agocwilson91
1 year, 4 months agoAbdelmonm
Most Recent 9 months agoOnly12go
1 year agoadingmaki
1 year agovictory108
1 year, 1 month agoAcmk
1 year, 1 month agoKelvin12312
1 year, 1 month agomiggykurkova
1 year, 1 month agoAYZ
1 year, 1 month agoAish_
1 year, 2 months agoSteAle
1 year, 3 months agomdadewale
1 year, 3 months agokevzzz
1 year, 5 months agospamgayy
1 year, 6 months agoRevZig67
1 year, 6 months agoSathy
1 year, 7 months agoRagaa
1 year, 9 months ago