Exam PMI-ACP topic 1 question 22 discussion

Actual exam question from PMI's PMI-ACP
Question #: 22
Topic #: 1
[All PMI-ACP Questions]


Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?

  • A. The team neglected to account for support and maintenance costs associated with other support products
  • B. The team discovered that previously accepted work could be greatly improved and added story points associated with that work
  • C. The team realized that some stories were underestimated relative to other stories and re-estimated as needed
  • D. The team learned that the product owner needed to increase the output in the next release
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nervys
11 months ago
C for sure
upvoted 1 times
...
Imrangoshi
1 year, 2 months ago
Selected Answer: C
C is the Correct Answer
upvoted 1 times
...
cutri89
1 year, 8 months ago
Selected Answer: C
i think this
upvoted 2 times
...
Petrevski
1 year, 8 months ago
Selected Answer: C
D - correct. A - not an option at all B - no one accepted work D - "need to increase" is not enough reason to add some points
upvoted 1 times
...
bhromorg
1 year, 9 months ago
D Is correct.
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: C
C is correct.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.