exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 50 discussion

Actual exam question from PMI's PMI-ACP
Question #: 50
Topic #: 1
[All PMI-ACP Questions]

An agile team is preparing a release plan for a project.
What information will the team need to complete this plan?

  • A. Amount of work needed to complete a single user story
  • B. Amount of work that can be accomplished by each team member
  • C. Amount of work that can be accomplished in an iteration
  • D. Amount of work that can be accomplished by the entire team
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
chlaithem
10 months, 1 week ago
Selected Answer: C
A. Individual user story effort: Knowing the effort required for individual user stories helps with backlog prioritization within each iteration, but it doesn't directly determine the overall iteration capacity. B. Team member individual work: Understanding individual team member capacity is helpful for resource allocation and workload balancing within the team, but it doesn't provide the whole picture of the team's collective capacity in an iteration. D. Entire team work: Knowing the total team capacity across all iterations can be helpful for long-term planning, but it's too broad for building the specific iteration-based release plan.
upvoted 2 times
...
itsmewajid
11 months, 2 weeks ago
Selected Answer: C
The release is the combination of Sprint(s). Now team will provide high level detail about how much work can be completed in each iteration.
upvoted 1 times
...
MattAnya
1 year ago
Selected Answer: C
There is a release at the end of each iteration
upvoted 1 times
...
Imrangoshi
1 year, 2 months ago
Selected Answer: A
A is the Correct Answer
upvoted 1 times
...
AKB968
1 year, 6 months ago
C is correct, cause the key point is after release is iteration, i.e, need to focus on iteration after release.
upvoted 1 times
...
Minhha3
1 year, 7 months ago
Vote C
upvoted 2 times
...
Petrevski
1 year, 7 months ago
Selected Answer: A
A = correct (in my opinion). Why? The first step to planning releases is to prioritize the user stories. Iterations are single units of work, within the release plan. So it is not enough to know just the amount of work that can be accomplished in an iteration. - Iteration planning focuses on the work in an iteration (it is a plan intended internally, for the development team). Iteration planning creates sprint tasks that teams must complete - Release planning prioritizes managing the product release from an iteration sequence. The release planning focuses on the final results and the user stories for product completion.
upvoted 1 times
Petrevski
1 year, 7 months ago
The release is focused on user stories vs. The iteration is focused on tasks, which are decomposed from user stores (meaning if you want to plan a release, first you need a user story, then the team will decompose it into tasks, based on, the team can plan the iterations within that release). The release consists of 2-4 iterations.
upvoted 1 times
...
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: C
C is correct.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...