exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 175 discussion

Actual exam question from PMI's PMP
Question #: 175
Topic #: 1
[All PMP Questions]

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.
What should the project manager have done to prevent this situation from happening?

  • A. Defined the skill requirements more clearly in the scope statement.
  • B. Asked the manager to follow the agreed-upon resource management plan.
  • C. Conducted periodic reviews with the manager on resource availability.
  • D. Consulted with the installation team on a regular basis to check for conflicts.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
atoms101
1 year ago
Selected Answer: B
If agreed resource management plan was followed then issue would be known before.
upvoted 2 times
...
Asakthi
1 year, 4 months ago
D. Consulted with the installation team on a regular basis to check for conflicts
upvoted 2 times
...
victory108
1 year, 6 months ago
Selected Answer: C
C. Conducted periodic reviews with the manager on resource availability
upvoted 1 times
...
JMCCRAY
1 year, 8 months ago
Selected Answer: C
The correct answer is C. Conducted periodic reviews with the manager on resource availability. By conducting periodic reviews with the manager on resource availability, the project manager could have identified the capacity issue earlier and taken proactive measures to mitigate the risk of a delayed equipment installation. This could have included exploring alternative installation teams or adjusting the project schedule to account for the delay.
upvoted 3 times
...
Hung3102
1 year, 9 months ago
C is answer. It is capacity issue. Option A (Defining skill requirements clearly in the scope statement) may not have addressed the specific issue of resource capacity and availability.
upvoted 3 times
...
AndU1
1 year, 11 months ago
I think A is correct.
upvoted 4 times
...
Weslineo
1 year, 11 months ago
There is capacity issue,which I believe is skill set not human resources problem
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...