A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?
Princessviv96
1 month agomartinx84
11 months agoDavonos
1 year, 8 months agotplummmm
1 year, 7 months agoMuntadher
1 year, 9 months agovictory108
1 year, 11 months agome4r2100
2 years, 3 months ago