The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.
What could have caused this?

  • A. The requirements matrix did not adequately track back to client requirements.
  • B. The product design was not properly reviewed by the quality department.
  • C. Requirement changes were not properly identified in the project charter.
  • D. The product was not adequately tested in accordance with the test plan.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlphaD
6 months, 2 weeks ago
A is best answer
upvoted 3 times
...
cslnm1
10 months, 1 week ago
"A" seems to be a better answer
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...