The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring.
Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring.
Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring.
Risk 4 has a US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring.
Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?
AhmedRashad
9 months, 2 weeks agoOMG4567
10 months, 1 week agoLunk
10 months, 2 weeks agoAzharmak
11 months agoemikhael
1 year, 4 months agoRoyalWarrior
1 year, 4 months agoemikhael
1 year, 5 months ago